CASE STUDIES

background
Home
CASE STUDIES
Edmonton/Hardisty Pipeline
PROJECT TYPE
OIL AND GAS PIPELINE
LOCATION
ALBERTA, CANADA
LENGTH / HOLE DIAMETER
3,700 M (2.3 MILES) TOTAL INSTALLATION / 1,219 MM (48 IN)
DIVISIONS
THE CROSSING COMPANY

Edmonton/Hardisty Pipeline

Horizontal Directional Bore

PROJECT SUMMARY

Our customer required multiple crossings be completed along the Edmonton Transportation Utility Corridor. This oil and gas pipeline was 914 mm (36 in) diameter, requiring a 1,219 mm (48 in) ream. The methodology used in these crossings is known as Horizontal Directional Bore which differs from Horizontal Directional Drilling in that there is no “belly” in the bore, and the drill path is a “straight shot” (versus a curved path). With the drilling rig being set further back, and drilling to depth, a catch pit was excavated for tooling changes and tie-ins.

6 RIGS 84 DAYS 24/7 OPERATION

KEY CHALLENGES

The timeframe to complete this horizontal directional bore pipeline crossing project was extremely limited. To accelerate the drilling schedule, six rigs were utilized. Working around the clock, three 45,360 kg (100,000 lb) rigs were assigned to complete the pilot hole and first ream passes. This was followed by three additional rigs (81,646 kg, 99,790 kg and 149,685 kg units) tasked with completing the final ream passes and product pull backs. We successfully completed work at all 18 crossing locations (3,700 m/12,139 ft total length) within 84 days.

SERVICES PROVIDED

HORIZONTAL DIRECTIONAL BORE

contact the crossing group

Home
CASE STUDIES
Edmonton/Hardisty Pipeline

Edmonton/Hardisty Pipeline

Description

Details

Project Type
OIL AND GAS PIPELINE
Sector
Pipline
Location
ALBERTA, CANADA
Trenchless Method
HDD

CHALLENGES

Outcomes

More case studies

Silverhope Creek Microtunnel

Read more

Jacko Lake Microtunnel

Read more

Sarcee Trail Crossing

Read more
No items found.